Once operational, it will be the country’s largest domestic terminal, one that will increase Tan Son Nhat's total capacity to 50 million passengers annually.
Le Khac Hong, head of the Terminal 3 project management board, said basic structural work has been completed for all components of the terminal, and teams are speeding up the architectural and construction work that remains.
The most crucial part, the 7,500-ton steel roof structure, was completed earlier this month after 120 days of accelerated work. The first layer of the aluminum roof, measuring over 42,000 square meters, has also been completed.