Failure to pay compensation to 8 households delays key HCMC road

By Quynh Tran   November 30, 2024 | 10:31 pm PT
A new road parallel to National Highway 50 connecting HCMC and the Mekong Delta planned to be completed this year may be delayed due to unresolved land compensation.
Failure to pay compensation to 8 households delays key HCMC road

The road, west of the highway, is nearly complete but is held up because eight remaining houses have not been acquired and their occupants have not been relocated.

Construction of the 4.3-kilometer road began in late 2022 with an estimated cost of VND1.5 trillion (US$59 million).

Some 75% of the road is complete, including a major portion in Binh Chanh District and the interchange where it runs into National Highway 50.

Failure to pay compensation to 8 households delays key HCMC road

Huynh Van Duyen, 53, owns one of the three houses. He says he cannot repair his 150-square-meter house, which is deteriorating and prone to flooding, since it has been earmarked for acquisition.

In 2010 his family accepted the government's offers of VND1.2 billion ($47,290) in compensation and the option to buy a nearby “resettlement” plot, he says.

"But I haven't received any compensation money yet, and Gia Hoa Company hasn't provided me with a clear compensation plan."

Failure to pay compensation to 8 households delays key HCMC road

Le Hong Duyen, who owns a 350-square-meter house (2nd, R), chose monetary compensation of nearly VND14 billion ($551,720) instead of land plots.

"The deadline has passed, but I haven't received any money,” she says.

I hope the company acts quickly so that the project can finish on schedule."

Failure to pay compensation to 8 households delays key HCMC road

The Transportation Works Construction Investment Project Management Authority of Ho Chi Minh City warns that the road might not open by December 2024 unless the households hand over their properties.

It has urged the city government to expedite compensation and direct Gia Hoa and Khang Phuc companies to finalize agreements and hand over the lands for construction.

Binh Chanh District officials are encouraging the owners to hand over their properties by the end of November 2024.

Failure to pay compensation to 8 households delays key HCMC road

The remaining sections of the new road have been paved. It is 34 meters wide and has six lanes.

Failure to pay compensation to 8 households delays key HCMC road

The median strip, drainage, electrical cables and sidewalks are mostly finished.

Failure to pay compensation to 8 households delays key HCMC road

Its four-meter-wide sidewalks are being paved.

Failure to pay compensation to 8 households delays key HCMC road

Construction of the Ba Lon Bridge, 40 meters long and 34 meters wide, on the new road is underway.

Failure to pay compensation to 8 households delays key HCMC road

Widening of a 2.5-kilometer section of National Highway 50 is expected to be completed next year.

This will affect 594 households, who are expected to be paid compensation of VND1.28 trillion ($50 million). But 15 households have yet to move out of their properties, delaying the work.

 
 
go to top