Work started on Ben Luc – Long Thanh Expressway nine years ago, but since 2019 it has stalled after the former contractor refused to continue working due to financing issues.
The expressway runs 57.7 km between Long An Province in the Mekong Delta and Dong Nai industrial hub, passing through Ho Chi Minh City.
Once complete, it will be the longest highway in southern Vietnam.
Costing VND31 trillion ($1.34 billion), the project uses investment loans from the Japan International Cooperation Agency, the Asian Development Bank and the Vietnamese government.
Explaining the lateness, the state-run Vietnam Expressway Corporation (VEC) in charge of the project said that several construction packages had been stalled as contractors had refused to continue working due to funding issues, although the site clearance process had been completed.
The government has recently solved the funding issue by allowing the VEC to use its own funds generated from operating other expressways.