$78M road along Dong Nai River takes shape

By Phuoc Tuan   November 27, 2023 | 07:51 pm PT
Costing VND1.9 trillion (US$78.3 million) and starting construction in 2021, a road and embankments along the Dong Nai River are expected to be complete in 2024.
$78M road along Dong Nai River takes shape

Covering a span of 5.2 kilometers, the road runs from Hoa An Bridge in southeastern Bien Hoa City, the capital of Dong Nai Province, to the province's Vinh Cuu District.

$78M road along Dong Nai River takes shape

Costing VND1.3 trillion, the road is in its final process of surface completion. The whole project is reportedly 50% complete.

$78M road along Dong Nai River takes shape

Construction workers are layering crushed stones with a vibratory roller before putting a layer of asphalt onto it to make the surface.

"We have handed over several sections of the road, with crushed stone already layered," said Hung, a construction worker.

$78M road along Dong Nai River takes shape

Divided into six lanes, the two-way roadway is designated to be 24-meter-wide, with two 5-meter-wide sidewalks run alongside its sides.

$78M road along Dong Nai River takes shape

Infrastructure for a lighting system has already been installed. Traffic signals, a drainage system, and trees are set to complete in the upcoming time.

$78M road along Dong Nai River takes shape

Rach Lung Bridge, part of the road, is almost complete. Vehicles can start passing over the bridge by the end of the year.

$78M road along Dong Nai River takes shape

The remaining VND600 billion of the project has been spent on constructing embankments and a riverside park, which started late last year.

According to the constructor, the project is 55% complete.

Construction workers can mostly work on construction processes when the tide has gone out only, lengthening the project’s duration.

$78M road along Dong Nai River takes shape

Several drainage sewers are being installed.

$78M road along Dong Nai River takes shape

Bien Hoa People’s Committee said issues in land clearance have slowed down the project’s construction process.

According to constructors, 30 households have not yet approved the compensation plan.

$78M road along Dong Nai River takes shape

Set to be completed in June 2024, the road is expected to motivate financial and social developments for Bien Hoa City and Vinh Cuu District, as well as improved urban architecture landscapes along the 586-km Dong Nai River, the longest that runs entirely in Vietnam.

 
 
go to top