Upgrade of the 3.2 kilometer (2 mile) long street, which connects downtown District 1 with District 2 through Binh Thanh District, was launched in October 2019 at a cost of VND470 billion ($20.39 million).
Work on the section from Ton Duc Thang Street to Thu Thiem Bridge has been completed, with the remaining section from Thu Thiem Bridge to Saigon Bridge still under repair.
Phan Duc, head of the project management board, said it is 70 percent complete and that work would commence through the upcoming Lunar New Year, or Tet, to complete before April 30.
The construction site currently hosts 70 types of machinery, equipment, transport vehicles and about 150 workers, including more than 50 for night shifts.