Vietnam PM orders 500kV circuit-3 power transmission project be completed by Sept 2

By VNA   August 13, 2024 | 07:05 pm PT
Vietnam PM orders 500kV circuit-3 power transmission project be completed by Sept 2
A worker of Vietnam Electricity (EVN) installs the 500kV power line in the central province of Thanh Hoa, June 2024. Photo by VnExpress/Loc Chung
Prime Minister Pham Minh Chinh has requested ministries, sectors, agencies, and localities to shorten timelines to complete the 500kV circuit-3 power transmission line project by Sept. 2, the National Day.

Chairing a meeting on the implementation of the project on Tuesday, the fifth held in the past seven months, the PM ordered the mobilization of human resources and equipment to ensure the progress, safety, and quality of the remaining workload, while conducting a trial run on parts of the system towards the whole project.

The project, running from the central province of Quang Binh to the northern province of Hung Yen, has a total length of about 519 km and an investment of VND22 trillion (US$875.62 million), with four component projects crossing nine provinces. Its construction started in January 2024.

To date, site clearance for 100% of pile foundation locations and route corridors has been completed, along with pole casting at 100% of locations, the erection of 1,159 out of 1,177 poles, and the construction and operation of the Nam Dinh 1-Thanh Hoa Power Plant sub-project.

The remaining works are mostly in the central provinces of Nghe An and Ha Tinh, which are expected to be finished by Aug. 18.

Pointing out difficulties facing the project, especially those from weather conditions and tough terrain, the PM requested contractors and workers to overcome all difficulties and maintain continuous work to ensure the project is completed on time.

He assigned detailed tasks to particular ministries, sectors, and localities, and directed all stakeholders to coordinate closely together to complete their missions.

The government leader also asked localities to remain cognizant of environmental protection and resettlement for affected communities.

In a dispatch issued in June to call for gathering resources for the project, the PM said the transmission line is critical to guaranteeing national energy security, helping improve the transmission capacity of the national power system, and ensuring power supply for the northern region during the peak period of 2024 and beyond.

 
 